EMC group to address permits for coal plant
CONYERS -- The group of EMCs planning to build a coal-fired power plant will have a chance to address issues in their permit application in response to a judge ruling issued earlier last week.
Courts rescind permits for coal-burning plant
Snapping Shoals EMC is still considering supporting the construction of a coal-fired power plant even after a judge recently reversed a decision to grant the project an air permit.